File sectionAreas of practice

Make the condition inside the production figure visible

01

Connecting a dispatch unit with the customer's continuous material requirement

I examine what the customer needs inside the unit our factory plans to dispatch. A group of 32 rolls in 2017 included eight that could not meet an agreed continuous-length requirement because of joins. I had supported the plan and retained responsibility for the ₹41 lakh rework that followed. A correct total length did not establish that each roll could support the intended operation. Later, twelve accepted rolls needed their winding presentation changed because the cores did not fit the agreed unwinder interface. That did not mean the felt's accepted material properties had failed. My contribution is to connect planning, commercial requirements and authorised acceptance before the quantity becomes a delivery promise, while keeping technical decisions and release with the qualified colleagues who own them.

02

Finding the reviewed destination before calling trim available for return

Recovered edge trim needs a destination whose requirements it actually fits. A reviewed 60-tonne group contained 42 tonnes compatible with the recipes being considered and eighteen tonnes that remained segregated. We funded a ₹76 lakh separation programme without describing the whole group as usable production input. The compatibility account did not establish a finished-product recycled-content percentage or a measured environmental benefit. I work with quality and technical colleagues to ensure that an operating proposal identifies the material's condition, the reviewed use and the portion still outside that use. Receipt into a recovery area is only one event. It should not silently become an assumption that the material can enter any recipe or that a programme budget proves a completed reduction in waste.

03

Keeping product weight inside the capacity comparison

A capacity assumption expressed in kilograms per hour changes meaning when orders are promised in square metres. At an assumed 600 kilograms per hour, a 400-gram-per-square-metre product yields a gross 1,500 square metres per hour, while an 800-gram product yields 750. Neither calculation establishes accepted output after trim, downtime and quality review. We deferred an ₹11.4 crore line proposal while funding a ₹92 lakh operating trial and planning programme. The smaller programme was a way to test the operating account, not proof that the larger investment was unnecessary. I want the product mix and the conditions behind a capacity figure to remain visible when operations and commercial colleagues assess whether a factory can support a particular demand.

04

Checking the machines a pooled spare can actually support

A pooled spare is useful only within the compatibility and recovery conditions that have been established. Our motor arrangement covered four machines in a six-machine group; two required different interfaces. We approved a ₹1.2 crore specific-spares programme to address the uncovered needs, retaining specialist authority over selection, installation and safe return to service. Additional inventory was not a claim that every failure could be resolved immediately or that maintenance risk had disappeared. I examine whether an operating resilience statement describes the actual equipment covered, the capability needed to use the spare and the limitations that remain. A common item name or a convenient stock location should not substitute for the engineering work that makes the proposed support credible in a particular installation.

How I lead

The roll is not the end of the operating story. A customer may need an uninterrupted length, a particular winding arrangement or a material recipe that cannot accept every returned fibre. I once counted a complete dispatch group without asking whether its joins allowed the next operation to run as agreed. Since then I have wanted the factory account to follow the material beyond the quantity we can conveniently report, including the limits of a capacity estimate and the equipment a spare can really support.

At scale

The responsibility, in figures

400

Operations colleagues

Five heads across Bhilwara and Ajmer; 560 company employees

₹94 crore

Annual operating delegation

₹7.2 crore capital separately approved

20 years

Manufacturing experience

Production engineering entry in July 2006

In practice

Decisions and their consequences

Case 01

Reworking eight rolls after I confused total length with continuous length

In 2017 I supported a dispatch plan for 32 rolls of technical felt. Eight contained joins that conflicted with the customer's agreed continuous-length requirement. The planning account showed the roll count and total length, and I had treated those measures as sufficient evidence that the group was ready for its intended use. The customer's next operation required an uninterrupted length that the affected rolls could not provide. That condition should have been visible before the plan became a delivery commitment.

We held the affected group and reworked the material, incurring ₹41 lakh. I owned the assumption in the plan rather than describe the issue only as a final dispatch-check failure. Quality and technical colleagues retained the decision about acceptance and the rework required. My responsibility was to make the customer condition part of the operating account and to ensure that the revised promise followed what could actually be supplied. The correction did not recover the cost or make the earlier representation accurate.

The difficulty was that familiar quantities had made the proposal appear complete. A roll count is useful for handling and transport; total length can support other planning questions. Neither necessarily describes the uninterrupted segments within each roll. We needed to explain which requirement the dispatch account was intended to satisfy and what evidence supported that conclusion. I did not respond by rejecting those quantities altogether, but by refusing to let them answer a question they did not resolve.

The result was a reworked group and a changed planning review, not a measured claim about every later delivery. The incident continues to shape how I examine production promises. Before approving a convenient summary, I want to know what the customer will do next and which condition inside the material could prevent that operation from working as agreed. That is an operating responsibility I cannot transfer entirely to the last person who sees the roll.

Case 02

Keeping eighteen tonnes outside the return recipe instead of counting all trim as available

A 2022 review considered a 60-tonne group of recovered edge trim for return to production. Technical and quality assessment identified 42 tonnes compatible with the recipes under review; eighteen tonnes remained segregated. The initial operating discussion had treated the full recovered quantity as available input. That would have moved too quickly from the fact that material had been collected to a conclusion about where it could be used. I asked the team to preserve the reviewed destination and the excluded portion in the planning account.

We funded a ₹76 lakh separation programme to make those distinctions workable in handling and production planning. The programme was not a declaration that all trim could enter all products, and the 42 tonnes did not establish any finished product's recycled-content percentage. The denominator for that claim would be different and would need its own evidence. Nor did the approved programme itself demonstrate an environmental saving. Those conclusions could not be borrowed from a recovery figure simply because they sounded like a natural continuation of the story.

The practical trade-off was to retain material outside the proposed use while making the compatible portion easier to manage. A larger apparent available quantity would have been attractive to the production plan, but only if its assumptions were true. Qualified colleagues retained recipe and acceptance authority. Operations had to support separation, records and the resulting constraints rather than ask those colleagues to approve a general return merely to make the material balance look better.

The case changed the language used in our operating discussion. Collected, reviewed as compatible and consumed in an accepted product were different states. We did not collapse them into one recovery achievement. My contribution was to connect the physical flow with the evidence required for its next use, including the eighteen tonnes still outside it. A credible circular-material proposal needs that unfinished account as much as it needs a description of the portion that can move forward.

Case 03

Reopening an area-capacity proposal built from one mass-throughput assumption

In 2023 a line-investment discussion used 600 kilograms per hour as its capacity assumption while commercial demand was expressed in square metres. The product mix included material at 400 and 800 grams per square metre. At the stated mass rate, the gross area calculations were 1,500 and 750 square metres per hour respectively. Treating the mass figure as one common area promise would have hidden a twofold difference before considering trim, downtime and acceptance. I asked that the investment account retain the mix rather than average away its consequence.

We deferred the ₹11.4 crore line proposal and funded a ₹92 lakh operating trial and planning programme. The programme was intended to test the assumptions and improve the demand-to-capacity account. Its approval did not establish an achieved rate or prove that the larger line would never be needed. The mass figure was an assumption for the comparison, not a demonstrated equipment output, and the arithmetic described gross material area rather than accepted customer supply.

Operations, technical and commercial colleagues needed to agree on the units used in the decision. Orders could not be assessed only in kilograms if their promised use was in area, and an area figure could not ignore the weight of the material being produced. The relevant operating losses and acceptance conditions also needed to remain visible. I did not treat the simple division as a complete capacity study; it was a way to expose an inconsistency before a more substantial commitment was made.

The outcome was a deferred investment and a funded programme of operating work, not a saving equal to the full line price. The larger proposal remained available for reconsideration after the relevant evidence. My lesson was to examine the unit in which a production claim is expressed and the unit in which the enterprise has made its customer promise. A number can be correct on its own terms and still be inadequate for the decision it is being asked to support.

Case 04

Funding the two machines left outside a pooled spare arrangement

A 2024 operating review described a pooled spare motor as support for a six-machine group. Engineering assessment established compatibility with four machines, while two required different interfaces. The shared item name and the existence of stock had made the coverage appear broader than it was. I asked that the resilience account identify the actual machines supported and the unresolved needs, rather than retain a six-machine claim because the arrangement was convenient to describe.

We approved a ₹1.2 crore specific-spares programme to address the uncovered requirements. Specialist colleagues retained authority over selection, installation and the conditions for safe return to service. The capital and inventory decision could support their work, but it did not replace it. Holding a compatible spare also would not establish that a future interruption could be resolved immediately, because people, diagnosis, installation and other operating conditions could still affect recovery.

The trade-off was to commit resources to less interchangeable support than the original pooled description implied. A single shared arrangement looked efficient in the stock account. Its value depended on actual compatibility, however, not on how many machines appeared beside it in a presentation. The review therefore had to preserve both the four-machine coverage and the two-machine gap. Neither fact should erase the other: the pool was useful within its limits, but the limits mattered to the claim being made about the factory.

The outcome was an approved programme and a more accurate support account. It was not proof of zero downtime or universal resilience. I would bring the same distinction into a board discussion about operating continuity. Directors should ask what assets and circumstances a mitigation actually covers, what remains outside it and which specialist decisions are still required. A reassuring stock figure becomes useful only when it is connected to the equipment and recovery process it is meant to support.

Case 05

Changing winding presentation without pretending the accepted felt had failed

In 2025, twelve rolls of otherwise accepted technical felt were held because their winding-core arrangement did not fit the customer's agreed unwinder interface. The material's accepted properties were not the issue identified in this review. Its presentation prevented the next operation from using it as intended. I asked operations to treat that condition as part of the delivery promise rather than assume that material acceptance made every downstream detail someone else's responsibility.

We reworked the winding presentation at ₹29 lakh cost, with the relevant technical and quality checks retained. I did not describe the work as evidence that the felt formulation had been wrong or that every roll in the wider order was affected. The twelve-roll scope and the interface requirement were kept explicit. The cost belonged to correcting a preparation problem, not to an asserted gain in product performance or an unmeasured improvement in customer loyalty.

The incident required production and commercial colleagues to connect their descriptions of the order. A specification may describe the material while another part of the agreement describes how it must arrive for handling and use. Both can matter to the customer's ability to start work. Operations needed a practical account of the interface, and acceptance needed to be understood within the scope it actually covered. No colleague's valid assessment should be extended silently into a conclusion about conditions they had not assessed.

The result was corrected presentation for the affected rolls and a clearer review of the handoff to the customer's process. It did not justify a claim that every future interface would be trouble-free. My responsibility as COO was to ensure that the factory's completion point did not end the story too early. A product can meet one set of requirements while still failing to support the operation for which it was prepared; the operating account should be capable of saying both things accurately.