Case 01
I approved the same maintenance month for sites with different wind
In 2016, as COO, I approved a common maintenance calendar across a contracted service portfolio. The arrangement simplified staffing and gave customers a concise annual availability account. Safiya Fezqarthi asked whether the local resource patterns justified using the same window at every site. I accepted the programme team's view that a consistent annual hours measure was sufficient for the commercial discussion. That was my decision, and it overlooked when the unavailable hours would occur.
At a six-machine customer cluster, planned shutdowns occupied fourteen days of a strong wind period. The subsequent review estimated 1.8 GWh of foregone generation against a stated operating counterfactual. That was not metered export, and weather and operating assumptions remained part of the estimate. The annual hours measure could still appear satisfactory while concealing a period with a different energy consequence. We had made the calendar easy to explain without adequately examining its value to that customer.
We accepted ₹1.4 crore in contractual customer credits. The credits followed the commercial arrangements; they were not a tariff-based valuation of the estimated 1.8 GWh. I also secured ₹1.8 crore for revised scheduling and service coverage. Operations, engineering and safety owners retained authority over the work itself. The correction did not mean moving maintenance into a period simply because a forecast looked attractive, or promising that every unavailable hour could be eliminated. It meant bringing the resource pattern, safe working conditions and customer commitments into the planning decision together.
The result was a different approval process and a real commercial cost, not proof of a precise amount of energy recovered later. The service programme became less uniform and required more coordination. I accepted that consequence because the apparent consistency had been purchased by ignoring a difference that mattered. In hindsight I would have asked Safiya to present the site-level objection before approving the common offer. The lesson was not that an hours measure is useless. It was that I had allowed one valid measure to stand in for the whole customer outcome.