Case I
Reopening a kiln proposal whose equipment price was not its cash requirement
In 2019, as head of planning, I endorsed a kiln proposal framed around a ₹9.8 crore equipment quotation. The account left out ₹1.4 crore of civil work, ₹1.1 crore of grid connection and ₹0.7 crore of startup cash. Those items brought the requirement to ₹13 crore. Operating colleagues had described work needed beyond the supplier's scope, but I had not assembled it into the proposal's funding account with sufficient care. The apparently precise equipment amount became a less complete statement about the enterprise's commitment.
We reopened the proposal and obtained additional approval for ₹3.2 crore. The project was delayed nine weeks. I retained responsibility for the framing instead of describing every omitted item as a later change by another team. The amounts represented project cash requirements; they did not establish that every item should be capitalised or receive identical accounting treatment. That assessment remained a separate professional responsibility. The immediate correction was to show the resources required to make the proposed equipment usable in its operating setting.
The consequence was more than an unfavourable variance in a report. Colleagues had planned around an incomplete funding account and needed a revised approval and sequence. We did not claim that identifying the omitted work created a saving or that the later approval recovered the delay. The supplier quotation could remain accurate for its own scope while our enterprise proposal was incomplete. Keeping that distinction visible made it possible to acknowledge the failure without inventing a fault in every underlying amount.
I changed the planning review so operating requirements had to be reconciled with the cash account before the equipment figure became the headline commitment. Finance needed to ask what made the project usable, not only what was being purchased from the principal supplier. I still use quotations as evidence, but do not let their precision imply completeness. The case remains a decision I supported inadequately, with the additional funding and nine-week delay retained as consequences rather than converted into a success story about discovering a more accurate number.