At the end of 2025, one production customer had paid CAD1.6 million in advance against a CAD4 million commissioned project. The delivery calendar had moved because the customer requested additional editing and the production team needed further clearance work. The cash forecast showed the advance as a useful receipt. A draft performance commentary gave the impression that receiving it had substantially completed the commercial task, even though the remaining work and acceptance conditions had changed.
I asked production, commercial and accounting colleagues to prepare a common account of what had been delivered, what was still owed and how the revised terms affected the project. The customer relationship lead wanted to avoid language that suggested a failing programme. The producer worried that a financial review would be read as criticism of editorial quality. I explained that the board needed an accurate account of the obligation, including the reasons for the delay, rather than a judgement inferred from the presence of cash.
The revised remaining-cost estimate rose from CAD900,000 to CAD1.15 million, a CAD250,000 increase. We obtained written agreement for an additional CAD180,000 customer fee associated with the changed scope. The net deterioration in the project's forecast margin from those two changes was therefore CAD70,000 before other movements. We retained the higher cost estimate even while part of the customer variation was still being documented, and we did not use the advance to offset the cost increase in the performance explanation.
Accounting colleagues assessed revenue and the advance balance against the actual contractual and delivery evidence. I avoided prescribing recognition from the receipt date. The programme was accepted in March 2026; the final cost and fee movements matched the stated revised amounts. The delay still consumed production capacity and management attention. The useful change was a clearer project account: advance cash, remaining work, agreed variation and financial reporting each had a place. A receipt that improved liquidity no longer made an unfinished obligation less visible to directors.
I would connect the advance receipt to the delivery schedule at contract approval, so the cash is not treated as freely available before the remaining work is understood.