A fixed-fee implementation was still reported against its original EUR2.14 million delivery-cost estimate on EUR2.8 million of contracted fees. The project team had identified additional effort, but the commercial discussion was waiting for a proposed scope agreement. If finance had left the original estimate in place until that negotiation ended, the account would have implied that an unagreed recovery already covered the work.
I asked delivery leadership to state the expected cost independently of the desired commercial answer. The revised estimate was EUR2.59 million, reducing forecast direct contribution from EUR660,000 to EUR210,000 before central overhead. The team then separated work within the existing commitment from additional scope to discuss with the customer. Contract interpretation and negotiation involved the appropriate commercial and legal colleagues; finance supplied the economics and timing.
The sales lead objected that recognising the lower forecast could make the negotiation seem unsuccessful before it had concluded. I argued that the two questions needed different dates. We could pursue a justified scope change without reporting its benefit as though agreement already existed. The executive review accepted the revised delivery view and gave the project the resources needed to maintain its obligations while the discussion continued.
The eventual agreement added EUR380,000 in fees and EUR100,000 of associated delivery cost. Forecast fees became EUR3.18 million and cost EUR2.69 million, leaving EUR490,000 of direct contribution. This was still an estimate of the completed project's economics, not cash collected, recognised profit for that month or group net profit. We kept the remaining work and customer dependencies under review.
I would introduce the commercial discussion earlier next time, before the cost change has accumulated into a difficult single revision. The lasting improvement was that a project manager no longer had to wait for a successful negotiation before admitting that the expected effort had changed. That made the account more useful at the point when management could still influence the outcome.