Case 01
Accepting sixty-four handover packs and keeping four with their unresolved owners
In July 2024 we reviewed sixty-eight digital handover packs intended for continuing property services. Forty-four contained the material the receiving teams needed. Twenty-four did not: sixteen lacked usable maintenance references and eight lacked clear warranty ownership. The files existed, and the visual models could be opened, but those facts did not answer the first practical questions facilities colleagues would face after the project team left. A complete delivery list was concealing an incomplete service handover.
The project sponsor wanted to accept the full set and close the technology workstream, with missing details to follow through ordinary support. Property operations objected that this would transfer unresolved work without a dependable owner. I supported a seven-week correction programme costing SGD1.6 million. We agreed the acceptance questions with the receiving teams and assigned the missing references and ownership decisions to the people who could supply them. My function coordinated the digital material; it did not substitute for the specialists responsible for its operating meaning.
Twenty of the twenty-four deficient packs became usable for the agreed service purpose. Four remained held, leaving sixty-four accepted packs and four explicit exceptions across the cohort. I kept the distinction in the programme report rather than count the existence of every file as acceptance. The outcome did not establish statutory occupancy permission, building safety or completion of the maintenance described. Those were separate matters with their own authorities. This examination concerned the quality of the digital handover to the continuing service team.
The decision delayed a simple project closure and required the sponsor to retain attention on material that was less visually impressive than the model. It also made the transfer more credible. The facilities team could identify what it had accepted and where the remaining answer would come from. I wanted the delivery milestone to mark a usable change in responsibility, not merely the movement of documents from one repository to another while the receiving team inherited the task of discovering what was missing.
I would involve receiving facilities teams when defining the handover pack, before document production begins, so acceptance criteria reflect the questions they will actually inherit.