Case 01
Buying a storage duty rather than a nameplate ratio
In March 2024, a storage proposal reached our technology review described as a twenty-megawatt, eighty-megawatt-hour system. The commercial presentation treated that pairing as a four-hour delivery promise. I asked the team to distinguish the nominal battery energy from the energy available at the agreed AC delivery boundary. That distinction changed the specification before it became a purchase commitment.
Our comparison used an explicitly illustrative year-ten condition. After the study's allowances for degradation, the operating reserve, conversion losses and auxiliaries, usable delivered energy was sixty-four megawatt-hours. This was a supplier-supported design assumption for evaluation at the specified temperature, not an observed operating result. Under that assumption, twenty megawatts lasted 3.2 hours; a four-hour interval implied sixteen megawatts. Neither calculation established availability across every temperature or proved performance throughout its operating life.
The development team preferred to preserve the larger power promise and address the energy shortfall during detailed design. Asset operations director Maren Solbrecht wanted a duty that the operating organisation could understand before taking responsibility for it. I recommended that we compare a sixteen-megawatt four-hour duty with a larger energy configuration, using the same delivery boundary and assumptions. This gave finance two defined alternatives rather than one attractive label with an unresolved addition behind it.
I authorised a €780,000, eleven-week qualification and specification programme. We retained the lower-power reference duty for procurement evaluation and postponed the commercial commitment while the alternatives were priced. The consequence was a six-week change to the tender calendar and a smaller headline power figure in the base case. We did not report a constructed asset, secured revenue or a saving from avoiding an addition that had never been ordered.
My contribution was to make the obligation testable. Specialists remained responsible for the detailed degradation model, electrical design and acceptance procedure. I required the board paper to state which number was nominal, which represented delivered energy and which conditions supported the proposed duty. If I repeated the work, I would settle that vocabulary when the commercial service was first proposed. Waiting until technology review allowed a convenient division of two nameplate values to acquire the authority of an engineering commitment.