Case 01
2023 — Keeping a storage proposition within the operating window it was designed to serve
The storage proposal at Norvelen Power began with an appealing specification: 10 MW power and 20 MWh nominal energy capacity. Commercial colleagues wanted a common product family for eight customer operating profiles. The difficulty appeared when we described the required service instead of the equipment. Five profiles involved a two-hour peak window; three required six hours. The same rating could not simply be placed beneath all eight customer accounts and allowed to imply the same service.
Owen Carvelen argued for keeping the full opportunity together while engineering developed the options. I understood the commercial reasoning. A broader family could attract more attention and keep all eight discussions open. My concern was that one development proposition would begin to carry two different duration expectations. The nominal ratio of 20 MWh to 10 MW is two hours; it is not six. Even the shorter ratio is not a complete delivered-service commitment, because actual usable energy, reserves and operating conditions require engineering assessment.
I supported C$14 million feasibility work around the five shorter-window profiles and removed the three six-hour profiles from this particular proposition. Those customers were not told that their requirements had disappeared. They needed a different development account. The decision gave up the appearance of one family addressing the entire opportunity and made the narrower commercial scope visible to the executive team.
We asked engineering colleagues to examine the intended service under the relevant site conditions, while product colleagues retained responsibility for describing the use case and its exclusions. The result recorded here is a bounded feasibility programme, not eight deployments, a certified operating duration or revenue from accepted orders. Neither the nominal rating nor my decision supplied the remaining technical approvals.
The experience changed the product conversation because the excluded customer became part of the evidence. I could explain why the proposal fitted five operating profiles well enough to investigate and why the other three required another approach. A specification becomes more useful when its relationship to a customer task is explicit. Allowing the larger opportunity to determine that relationship in advance would have made the development brief less honest and the eventual service discussion harder.