Case 01
Keeping the irregular-parcel station beside a faster sorter
In November 2023, a warehouse automation proposal depended on achieving 1,500 accepted parcels per operating hour. The equipment could briefly run faster than that with suitable parcels, but the investment assumption concerned the entire operating period. Our existing line averaged 1,040 accepted parcels per hour across six examined shifts. Irregular items, recirculation and feeding interruptions made the surrounding process important to the result.
I authorised a twelve-week, JPY84 million development and assessment programme. The team revised the diversion arrangement and examined six further shifts with broadly comparable work mix. The revised system averaged 1,270 accepted parcels per operating hour. This was an observational before-and-after comparison, not a controlled estimate of the machinery's isolated effect. It also remained below the original investment assumption, despite representing a useful improvement in the examined operation.
The project sponsor wanted to remove the irregular-parcel station to release floor space and present a simpler layout. Mika Nerutani's team showed how staff used that station to keep unsuitable items from disrupting the main flow. I supported retaining it and changed the proposed four-site release into a two-site learning stage. Procurement lost some anticipated purchasing simplicity, and the project kept a staffing requirement that its early presentation had expected to reduce.
We revised the next-stage account around the observed whole-shift rate and the work retained outside the sorter. The additional sites were not cancelled permanently; they needed a stronger operating basis before approval. We did not claim that the difference between the two six-shift averages represented an assured network improvement or a realised labour saving. The result supported further learning at a defined scale while preserving the cost of the remaining work.
The important change was the unit of discussion. Instead of asking whether the machine could reach a short-run rate, we asked whether the warehouse could sustain the intended service with its actual parcel mix. I would involve irregular-item handlers before fixing the first layout. Their work was not a temporary embarrassment to be removed from the account; it was part of understanding where the proposed automation was useful and what the surrounding operation still needed.