Harunori MitsuseLeadership review 2026

Areas of practice · 2026

Equipment capability meets the ordinary demands of a depot

01

Whole-shift automation economics

I examine accepted work across an operating period, including feeding, recirculation, irregular items and recovery time. A machine's short-run rate can help specify its capability without describing the throughput of the surrounding service. I ask the project team to identify where work accumulates and who handles the items outside the preferred range. In our sorter review, better observed shift output still fell short of the investment assumption. Keeping an irregular-parcel station made the proposal less tidy but more usable. My role is to connect that engineering account with the staffing and space that operations must provide. I also want the denominator stated: scheduled time, running time and an examined shift are different bases. A useful recommendation explains why the selected evidence supports the next stage and which assumptions remain to be tested before wider adoption.

02

Mobile equipment in a workplace shared with people

I treat robot movement as part of workplace design, with operating specialists and safety professionals involved from the beginning. A shorter machine route may compete with a pedestrian crossing or a replenishment task. My team examines the resulting pattern of waiting and movement rather than using robot distance alone as the score. In one investigation, we accepted a longer route around a busy crossing and kept the change within a defined operating assessment. A performance trial does not replace the site's separate safety review or establish that a layout is suitable everywhere. I want workers' observations recorded as engineering information, especially when the inconvenience appears outside the machine's immediate mission. This helps us decide whether a proposal makes the whole workplace more workable instead of merely improving the device's own travel account.

03

Delivery electrification grounded in depot time

I connect vehicle duty, return time and the available charging window before interpreting a fleet trial. The service can finish successfully because operations substitutes another vehicle, so completion alone does not establish that each original assignment was feasible. Our eight-van winter study retained fourteen substitutions within its account of 126 completed duties. I worked with operations to preserve the reserve requirement in the next proposal rather than call it an incidental trial expense. Electrical specialists assess the installation and supply constraints; my responsibility is to make those dependencies visible in the adoption decision. Seasonal conditions, payload and route patterns also affect the evidence we need. I do not turn one depot's findings into a universal range or cost claim, and I keep the purchase timetable separate from readiness to support the vehicles in service.

04

Maintainability and packaging as operating capability

I look at what a physical system asks the organisation to know and protect. A conveyor needs understandable maintenance information and supported practice; a parcel needs packaging suited to the hazards its contents will face. Neither responsibility ends with a supplier delivery. I bring technicians, packaging specialists and operating owners into the definition of a useful handover, while keeping their specialist judgements distinct. The maintenance exercise showed where course completion had been mistaken for demonstrated independence. The packaging study showed why a material preference still needed a protection assessment before release. In each setting I want procurement to include the work required after acceptance, not simply the item being purchased. That creates a clearer account of development cost and continuing capability, with unresolved findings attached to an owner who can decide the next step.

How I lead

I want a machine's useful contribution assessed beside the people, space and maintenance arrangements that allow it to keep contributing.

At scale

The responsibility, in figures

120

Engineering employees

Five direct reports, plus twenty-four contractors separately

JPY3.8bn

2026 engineering authority

Development JPY2.4bn; support and capability JPY1.4bn

31 years

Physical-systems experience

Equipment supply and logistics, April 1995 onwards

In practice

Decisions and their consequences

Case 01

Keeping the irregular-parcel station beside a faster sorter

In November 2023, a warehouse automation proposal depended on achieving 1,500 accepted parcels per operating hour. The equipment could briefly run faster than that with suitable parcels, but the investment assumption concerned the entire operating period. Our existing line averaged 1,040 accepted parcels per hour across six examined shifts. Irregular items, recirculation and feeding interruptions made the surrounding process important to the result.

I authorised a twelve-week, JPY84 million development and assessment programme. The team revised the diversion arrangement and examined six further shifts with broadly comparable work mix. The revised system averaged 1,270 accepted parcels per operating hour. This was an observational before-and-after comparison, not a controlled estimate of the machinery's isolated effect. It also remained below the original investment assumption, despite representing a useful improvement in the examined operation.

The project sponsor wanted to remove the irregular-parcel station to release floor space and present a simpler layout. Mika Nerutani's team showed how staff used that station to keep unsuitable items from disrupting the main flow. I supported retaining it and changed the proposed four-site release into a two-site learning stage. Procurement lost some anticipated purchasing simplicity, and the project kept a staffing requirement that its early presentation had expected to reduce.

We revised the next-stage account around the observed whole-shift rate and the work retained outside the sorter. The additional sites were not cancelled permanently; they needed a stronger operating basis before approval. We did not claim that the difference between the two six-shift averages represented an assured network improvement or a realised labour saving. The result supported further learning at a defined scale while preserving the cost of the remaining work.

The important change was the unit of discussion. Instead of asking whether the machine could reach a short-run rate, we asked whether the warehouse could sustain the intended service with its actual parcel mix. I would involve irregular-item handlers before fixing the first layout. Their work was not a temporary embarrassment to be removed from the account; it was part of understanding where the proposed automation was useful and what the surrounding operation still needed.

Case 02

Giving six mobile robots a longer route around a busy crossing

A June 2024 investigation examined six mobile robots serving a warehouse replenishment area. The shortest mapped route crossed a pedestrian path used by staff moving between workstations. The operating team described frequent interruptions to its own movement, while the initial project account concentrated on robot travel distance. The equipment was not being judged against the full set of activities sharing the space.

We funded a ten-week, JPY62 million programme to examine alternative layouts with operating staff and the relevant safety specialists. Within the performance assessment, four eight-hour observation days recorded the original arrangement and four examined a revised route around the busy crossing. Average completed replenishment missions per observation day moved from 286 to 274. The median observed pedestrian wait at the examined crossing moved from twenty-eight to nine seconds. These were selected observations under the two arrangements, not a randomised study or a measure of every movement in the warehouse.

The automation sponsor preferred the higher robot mission count and wanted more time to optimise the shortest route. Mika's team argued that the additional waiting burden had been transferred to people whose work was absent from that score. I supported the longer route for the next operating stage, accepting the lower observed mission count. We kept the replenishment requirement in view rather than declare a lower machine output intrinsically desirable.

The revised arrangement proceeded only through the site's separate safety and operating review. Neither the waiting-time comparison nor the absence of an incident during observation established safety. The technical specialists retained responsibility for assessing the actual installation. My decision concerned the investment and the performance account: a device's efficient route should not receive all the credit while another group carries an unmeasured cost.

The case changed our layout workshops. We began by listing the journeys that shared the space, including those without a machine-generated mission record. I would now bring those users into the first concept discussion, before a shortest-route drawing becomes the assumed design. A longer path can be a sensible operating choice, but it needs to be justified by the work it enables and checked in the real workplace, not celebrated as a general rule for robot deployment.

Case 03

Counting vehicle substitutions inside an electric-van trial

In January 2025, we began a twelve-week winter assessment of eight electric delivery vans at one depot. The JPY48 million programme examined how the selected vehicle duties fitted the actual return schedule and available charging windows. It was a development trial within a larger delivery operation, with reserve vehicles available. The initial success measure was completion of the 126 planned duties, which risked concealing how that completion was achieved.

All 126 duties were completed, but fourteen required a planned substitution because the van originally assigned to the duty had an insufficient charging window. Those fourteen duties were served by reserve vehicles. We did not describe them as customer delivery failures, and we did not count them as evidence that the original electric assignment worked unchanged. The record separated the customer outcome from the engineering feasibility of the assignment.

The procurement sponsor wanted the complete service record to support an immediate move from eight to twenty-four vans. I recommended retaining the eight-van stage while revising duty allocation and the charging plan. Mika Nerutani agreed to keep reserve capacity explicit in the next operating proposal. This delayed the larger purchase and retained a support cost that would have disappeared from a simpler completion-only narrative.

Electrical specialists reviewed the installation and supply assumptions, while fleet and depot teams examined return times, payload and the next departure. My responsibility was to connect those dependencies in the investment recommendation, not prescribe electrical settings or claim a universal vehicle range. The winter observations did not establish annual energy cost, emissions or performance at other depots. We kept those questions separate from the immediate decision about expansion.

The trial improved the way we discussed operational readiness. A completed service can be a useful result and still depend on resources outside the proposed standard design. I would agree the treatment of substitutions before the next trial begins and ask the sponsor to show which of them would remain affordable in ordinary operation. That makes reserve capacity an accountable design choice rather than a hidden favour supplied by the wider fleet during a demonstration.

Case 04

Revising a fibre insert before approving a packaging change

An August 2025 packaging project proposed a fibre insert for a selected fragile product. Procurement wanted to reduce use of the existing plastic insert and simplify the material account. Our responsibility was to establish whether the proposed package protected its contents under the chosen assessment before changing the service. A material preference could define a development objective without settling the protection question.

The JPY31 million programme used a defined laboratory sequence representing selected handling hazards. Forty packages with the proposed insert and forty with the current insert were assessed. Seven products in the proposed group and two in the current group showed the specified damage. These were observations in a selected test, not estimates of the customer damage rate. The protocol and product configuration remained attached to the result.

The procurement sponsor preferred a quick launch followed by field monitoring. I supported revising the insert first, accepting a later release and additional development work. Packaging specialists changed the support around the vulnerable part of the product. A further forty packages with the revised insert produced one observed damaged product under the same defined sequence. That repeat justified a limited field evaluation; it did not establish that every route, product or handling condition would behave the same way.

We retained the product-protection decision separately from any environmental assessment. The project did not make a comparative life-cycle claim or treat a material substitution as sufficient evidence of lower overall impact. The next-stage account included the revised insert, its cost and the need to observe performance in the intended service. The original launch message was deferred while the engineering and procurement teams agreed what the evidence actually supported.

The enterprise gained a more useful relationship between packaging development and purchasing. The supplier was not simply asked to deliver a preferred material at a chosen price; the team had to show how it supported the particular product. I would define the damage criterion and field-evaluation plan at the first briefing, alongside the material objective. That would make a disappointing first result a foreseeable part of development rather than a late obstacle to an announcement already prepared.

Case 05

Buying supported maintenance practice, not just course attendance

Between February and August 2026, an automation programme prepared technicians at two depots to support a new equipment family. The supplier course had been completed, and the release plan treated attendance as evidence that the receiving organisation was ready. Supervisors were less certain that the written material connected the symptoms they would encounter with the investigation the course had demonstrated.

We authorised JPY46 million for a six-month capability programme, including a defined practical assessment. Thirty-six technicians attempted the same selected fault-diagnosis exercise under supervised conditions. Twenty completed it without prompting; sixteen required support. That was evidence about one exercise after a particular learning experience. It was not a ranking of overall competence, a safety certification or a finding that sixteen people could not maintain the equipment.

The project sponsor wanted to proceed because the supplier's course obligation had been met. I recommended adding supervised practice and revising the documentation before expanding the equipment footprint. We funded JPY12 million of additional work and kept the next depot introduction pending its capability review. The choice added cost and delayed a planned introduction, but it made the receiving team's actual preparation part of the delivery obligation.

Technicians helped identify where the material assumed familiarity that had not been established. Supervisors and supplier specialists revised the explanation of the selected diagnostic task and created supported opportunities to practise. The follow-up assessment remains under evaluation in October 2026. I do not report a completion rate for it or imply that the first exercise's results have already been resolved.

The case changed how I frame maintainability in procurement. Documentation, access to specialist help and the time needed to practise belong beside equipment performance in the handover discussion. I would agree the practical evidence earlier, while the supplier still has a clear development responsibility and the receiving team can influence the plan. Learning gaps should be found in conditions designed to support learning, rather than discovered during an interruption when a technician is expected to satisfy an assumption someone else made at project approval.