Case I
Extending the programme to keep occupied buildings workable
In 2020, we prepared an initial €22.2 million refurbishment programme across seven occupied properties covering approximately 96,000 square metres. The initial eighteen-month sequence concentrated work into periods that suited procurement and construction efficiency. Several tenants explained that the proposed access and disruption would interfere with important operating activities. The project team believed a longer programme would add cost and increase the number of interfaces to manage. Both positions reflected a real consequence of the choice.
I asked the asset and project teams to develop a thirty-month alternative, with tenant operating needs included before the sequence was fixed. Qualified specialists retained responsibility for technical methods and safe execution. The revised plan added €1.8 million in preliminaries and coordination expenditure, bringing the approved programme to €24 million. I accepted that cost rather than present reduced disruption as a benefit available without a commercial sacrifice. The board received the longer timetable and the additional expense together.
The programme was completed under that phased approach. Six of eight anchor tenants whose leases came up for decision renewed; two left. We did not attribute all six renewals to the works, because rent, business conditions and location also affected their decisions. Metered purchased energy across the reviewed properties was 21% lower in the subsequent comparison period, with occupancy and weather differences limiting the conclusion. We did not turn that observation into a verified carbon result.
The outcome was a workable refurbishment sequence with an acknowledged cost, not universal tenant retention or a disruption-free project. Some occupiers still found particular phases difficult, and their feedback changed later coordination. I learnt that involving tenants early has value only if management is willing to alter the programme when their evidence warrants it. Consultation that leaves the original sequence untouched can create the appearance of consideration without changing the experience inside the building.
Looking back, I would put tenant access constraints into the first programme discussion, before a completion date starts shaping expectations that occupied buildings cannot reasonably meet.