Our 2022 recovery rehearsal reached a technical restoration milestone at hour six. The agreed business flow, involving the authorised people and the connected records needed to transact, completed at hour twenty-nine from the same starting point. Reporting six hours alone would have suggested a degree of operating readiness the exercise had not established. This was a planned rehearsal, not a live attack or an actual factory outage.
I asked that both milestones remain in the executive account. The difference was not twenty-nine additional hours after restoration; it was twenty-three further hours within a total elapsed period of twenty-nine. That distinction mattered when colleagues discussed the scope of recovery. We needed to know which dependencies remained after the systems were available and which process owners had to participate in proving that work could resume.
We funded a ₹71 lakh recovery programme to address the dependencies exposed by the rehearsal. I coordinated the systems work with operating owners, while Shalini Neqvashi retained responsibility for operating priorities. The programme's approval did not establish a later recovery time. A further exercise would need its own conditions and evidence before we could claim a changed result.
The trade-off was to retain a less reassuring but more useful account. Technical teams had achieved an important milestone, and that achievement did not need to be dismissed. It needed to be placed beside the business work still incomplete. I wanted the board discussion to examine the enterprise's ability to transact under the tested conditions, rather than infer that ability from a restored screen.
The case gave us a more precise basis for recovery planning. It did not prove readiness for every disruption, nor did a rehearsal reproduce all the uncertainty of an actual incident. My contribution was to insist that the reported endpoint correspond to the question management and directors believed they were asking.