Paying for the flame instead of the form in Amravati
We opened our first domestic network in Amravati in October 2019. Like every authorised entity, we had licence commitments to connect a large number of homes within a fixed period, and our first plan rewarded speed. Seven agencies ran registration camps and were paid ₹250 for each completed form. By March 2020 we held 62,000 registrations. Only 21,700 homes had gas flowing, and only about 15,100 of those used more than five standard cubic metres a month. The rest had a meter on the wall and a cylinder still on the stove.
The stakes ran beyond one city. A registration that never became a consuming home cost us between ₹4,000 and ₹17,500, depending on how far installation had gone. When lockdown halted work in 2020, I proposed a different contract: nothing for forms; ₹900 to an agency for each household still consuming sixty days after gas-in; installation contractors paid on gas-in within forty-five days of registration; and ₹1,000 at registration, with the rest of the connection charge spread over twelve bi-monthly bills.
Our head of projects disagreed. His team reported progress against licence commitments, and he expected the change to slow the count he was measured on. The fund's nominee director asked what penalty exposure we were accepting. We agreed that projects would keep reporting licence progress on the regulator's definitions while the board pack led with consuming households.
Registrations fell from about 5,200 a month to 3,100 for two quarters. Three of the seven agencies left, and deferred connection charges added ₹14 crore to our balance sheet by March 2022.
By 2022–23, 78 per cent of registered Amravati homes were gassed in within ninety days, against about 35 per cent within six months under the old contract, and 91 per cent of gassed-in homes were still consuming after sixty days, against 70 per cent. All-in acquisition cost per consuming household fell from ₹31,400 to ₹21,800. Amravati reached 96,000 consuming households by March 2026, and the contract became our standard in every area.
What I would do differently: I designed the change with finance and the agencies but not with the projects team, whose contractors absorbed the rework. I would also have secured meter stock first. For two months, homes waited for meters that agencies had been paid to hurry.