Roxanne DarsheviChief Operating Officer · Essays & perspective
← All essays

Bulky-product access planning5 min read

The patio dimensions did not describe the delivery route

A product can fit its destination while failing to reach it. Earlier access planning changed the customer promise and required us to accept time and expense before dispatch.

## The missing space was between the measurements

The furniture was suitable for the patio in the sales drawing. The customer had checked the intended space, and the product dimensions were recorded. What the account did not adequately describe was the route through the property. Doors, stairs, turns and permitted access could prevent the packaged sections from reaching the place where the furniture would be used. The delivery crew encountered that problem after the customer had already organised a day around the visit. A process that looked complete before dispatch had left a consequential question for the most inconvenient moment.

In FY2023, eighty-two of 640 attempted orders failed at the first visit because of access constraints. That count made it difficult to describe the problem as a handful of unforeseeable exceptions. I had accepted a planning approach that collected dimensions without asking whether they answered the whole delivery question. The omission was familiar from my earlier exhibition work. A stand component could fit its final position and still fail to pass through the venue's loading entrance. I had learned the principle but had not made it sufficiently explicit in the retail operation I led.

The commercial objection to more planning was reasonable. Additional questions could make a customer hesitate, and a site visit could lengthen the time before a delivery date was confirmed. Some colleagues believed experienced crews could resolve most difficulties on arrival. That view underestimated what we were asking the crew to absorb. The customer expected a usable result, the vehicle had other commitments and the team might lack either the equipment or authority to change the method. Experience matters, but it cannot reliably compensate for an access condition the business has chosen not to establish.

We needed to distinguish routine planning from specialist judgement. A delivery planner can collect relevant measurements and explain the proposed route. That does not make the planner competent to certify structural suitability or authorise a different lifting method. The process had to identify when the question required somebody else's assessment. I did not want earlier planning to become a new source of false confidence, with a completed form treated as proof that every technical condition had been satisfied. The useful account would say what had been checked and which conclusion remained with a qualified owner.

## Change the promise while it can still change

We funded ₹26 lakh of planning, measurement and training work. The questions became more specific to the access required, and site visits were arranged with permission when appropriate. We collected what was needed for the delivery decision rather than accumulating unnecessary detail about a customer's home. The objective was a workable plan, not a comprehensive property record. That distinction helped the team explain why a measurement was being requested and when a different kind of review was needed. Customers could then understand how the answer affected the proposed visit.

Where the review was required, the planning allowance added three days to the promise. I wanted that consequence stated openly. A process that takes time should not be presented to sales as though it can be inserted invisibly between an order and an unchanged deadline. Some orders could proceed without the same level of review, but the difficult ones needed a credible allowance. A slightly later date could be less attractive at the point of sale while producing a more honest commitment. The commercial team still had to explain the tradeoff and accept that some customers might choose differently.

Earlier knowledge also created alternatives that were harder to consider on the doorstep. A different configuration might fit the route. The delivery arrangement might need specialist review. In some circumstances cancellation under the relevant terms could be the appropriate outcome. Those choices belonged with the authorised commercial and professional owners, not with a crew under pressure to improvise. I would rather the business explain an unsuitable original arrangement while there is time to reconsider it than make the delivery team the last point at which the promise can be questioned.

The change affected how operations and sales worked together. We could not simply add a checklist and assume the handoff had improved. The result of the review needed to reach the people confirming the date and preparing the visit. If a condition changed, the plan needed a clear route back for reconsideration. The important object was the usable delivery commitment, not the completed planning document. I asked managers to follow the decision through those handoffs so that a useful measurement did not remain in one record while another team acted on the original assumption.

## Use the improvement without overstating it

A later FY2024 cohort recorded thirty-five access-related first-visit failures among 720 attempted orders. That was a better observed result than eighty-two among 640, and it supported continuing the approach. The cohorts nevertheless differed in period and order mix. We had not run a controlled experiment that isolated planning from every other influence. I therefore avoided claiming that the process alone caused the whole improvement. A leadership account should be able to recognise useful progress without pretending the evidence is stronger than it is. The remaining failures also required attention in their own right.

The count concerned access-related first-visit failures, not every delivery defect or every customer outcome. It did not establish that each successful arrival led to a technically accepted installation. Those are further questions with their own evidence. Compressing them into a single success percentage would have made the result sound more complete while reducing its usefulness. I wanted the review to identify which problem we had examined, what changed in that problem and where the next operating question began. That is how a measure can guide action rather than become a general badge of performance.

For directors, the relevant issue is the basis of the promise management is making. A board does not need to review individual door measurements. It can ask whether a material delivery dependency is established before the company commits, what the additional planning costs and how exceptions are handled. It can also ask who has authority when the question becomes technical. Those are oversight questions about the operating model. They help management keep a commercially attractive offer connected to the physical conditions required to deliver it, without moving the board into dispatch supervision.

I would now begin the review of a bulky-product service by following the object from the vehicle to the place it will be used. That simple exercise exposes assumptions hidden between otherwise accurate dimensions. The patio measurement was not wrong; it was insufficient for the promise we had built around it. Our change added expense and time, and it did not remove every failed visit. It did give the company a better opportunity to make a workable choice before a crew and customer were committed to the day. That is the operating responsibility I should have made explicit sooner.