The equipment quote left ₹3.2 crore of project cash outside the proposal
Civil work, grid connection and startup needs took the cash requirement from ₹9.8 crore to ₹13 crore. I owned the incomplete framing, with additional approval and a nine-week delay. The amounts describe project cash, not a claim that every item should be capitalised.