Nine assemblies challenged the loaded-use claim I had endorsed
Nine of thirty reviewed assemblies missed the project's acoustic criterion under loaded conditions. We held 120 preproduction units, delayed introduction ten weeks and incurred ₹48 lakh in correction work. The earlier unloaded demonstration did not establish the claim I had allowed it to support.