Repeated loading challenged my initial approval
An initial static check had looked satisfactory, but a later forty-rig review found 28 holding position and twelve tilting under the repeated-load test. We held 240 preproduction units before shipment, spent ₹62 lakh on redesign and accepted a seven-week delay.