An introduction

From the approved drawing to the welded joint


Every cut, weld and inspection should trace back to the drawing revision a customer approved, on machines we know how to protect.

Australia

Open to Board appointments

Start a conversation
My approach

An old machine is not automatically a security failure, and a new robot is not automatically progress. Both are decisions about who touches the work, which instruction they follow and how we would prove it later. I want the technology function to answer those questions before a customer, an auditor or a welder has to ask them.

Group revenue
A$238m
Year ended June 2026; about 61 per cent from defence work
Employees across three sites
712
Including 46 apprentices; Wingfield, Edinburgh and Henderson
CNC machines in service
63
Nineteen older controllers now isolated behind a program server

Work worth discussing.

01Isolating nineteen older CNC machines before replacing any of them

In 2021 a security review, prepared ahead of a naval customer's supplier audit, found that nineteen of our sixty-three CNC machines loaded programs from computers running an operating system its vendor no longer supported. Machinists moved programs on USB sticks. Four of the nineteen controllers also had failing parts that were becoming hard to source. Our production general manager and chief financial officer favoured replacing eleven machines at a quoted A$13.4 million, arguing that new equipment would add capacity and settle the auditors' concern in one move.

I recommended a different first step. We separated the machine network from the office network, installed a program server that released only approved, revision-matched programs, sealed the USB ports, locked the old computers to the applications they needed and retrofitted the four failing controllers. The cost was A$1.9 million over nine months. The trade-off was real: we gave up the capacity new machines would have brought, and machinists lost a quick habit they valued. The production general manager told the board that program loading would slow the night shift, and for two months he was right.

Finance also worried that the customer might still insist on replacement and leave us paying twice. I asked the customer's security team to review the design before we built it; they accepted it with two changes.

By month nine every program reached those machines through the server. Controller-related stoppages fell from 31 hours a month to nine, mainly because of the retrofits. The audit closed with two minor findings, both about documentation. In 2024 we replaced three of the nineteen machines, for A$4.6 million, on capacity grounds the board considered separately.

What I would do differently is involve the machinists before the first design. Our initial version required walking to a terminal at the end of each bay to request a program. A request screen at each machine, added in month three, should have been there from the start.

02Building the drawing-to-inspection path for defence work first

By 2022 our naval customers issued three-dimensional models with manufacturing information embedded, and revisions arrived as often as weekly while a structural unit was in build. Our shop still worked from printed drawings and paper travellers. In the 2022 financial year we recorded 41 revision-related nonconformances on defence work, and one batch of machined seatings made to a superseded revision cost A$212,000 to scrap and remake.

The general manager of our commercial division, which serves water and transport customers, proposed one cloud-hosted product lifecycle tool for all work, quoted at A$2.1 million and deliverable within a year. I did not support it for defence data. Some of the technical data we receive is export-controlled, and our customers' contracts set conditions on where it may be held and who may view it. Our export-control officer could not confirm that the proposed service met those conditions, and the vendor could not do so without qualifications.

I recommended building the path from model to traveller to inspection result for defence work first, inside a separately administered environment with named access, at A$3.6 million over two years. Commercial work would stay on paper for eighteen months longer. The commercial division lost a faster improvement, and we accepted the cost of running two systems. The chief executive and board approved the plan; the commercial general manager's argument for speed was sound, and I said so in the paper.

Revision-related nonconformances on defence work fell to six in the 2025 financial year. First-article inspection of a typical seating fell from 5.5 hours to 3.2, because inspectors received the correct model characteristics with the part. In 2025 commercial work moved onto a simpler, separate instance costing A$0.8 million.

I would now ask the export-control officer and the customer's security team to write the access requirements with us at the outset. We spent four months redesigning permissions that a joint workshop in the first fortnight would have settled.

03Installing one welding robot and making welders its programmers

In 2024 we prepared a tender for repeat structural units on a naval programme, worth up to A$46 million over five years. A large share of the welding was stiffener-to-plate joints of stable geometry. Our owners and the chief executive favoured three robotic welding cells costing A$7.8 million, which would have supported a sharper price. Adelaide was short of experienced welders, and the case for automation was strong.

My concerns were qualification and people. Every robotic weld procedure for naval work needs its own qualification testing before production, and we had not yet qualified one. Three cells would also need operators we did not have, and our welders' representatives feared the cells were a first step towards fewer welders. I recommended one cell, qualified for the two most repeatable joint types, with eight experienced welders trained as its programmers and operators at their trade rate plus an allowance. Complex nodes and closing welds would remain manual.

The trade-off was price. Our tender was about 3.5 per cent higher than the three-cell model implied. A family director argued that we were handing the contract to a competitor. Our welding supervisor, Kerri-Anne Mulcaster, doubted at first that the cell would ever match her best welders.

We were awarded a reduced share of the programme, about A$31 million, with another supplier taking the remainder. The cell cost A$2.9 million. Procedure qualification took seven months rather than the four I had planned. Once running, the cell reached 58 per cent arc-on time against 22 per cent for manual welding of the same joints, with first-pass acceptance of 97.4 per cent. Nobody lost a position. In 2026 the board approved a second cell on the evidence of the first.

What I would do differently is qualify the robotic procedures before the tender rather than during it. The board would then have priced the work on demonstrated capability instead of my estimate, and the reduced share might have been larger.

I make the path from an approved drawing to a finished, inspected part traceable, protected and workable for the tradespeople who build it.

I am chief technology officer at Kestwater Engineering, a privately owned fabrication and precision-machining company headquartered in Adelaide. We build structural assemblies, machined fittings and seatings for naval shipbuilding and sustainment, and pump skids, pipework spools and bridge bearings for water and transport customers. Revenue for the year ended June 2026 was A$238 million, about 61 per cent of it from defence work. We employ 712 people at Wingfield and Edinburgh in South Australia and at a sustainment workshop in Henderson, Western Australia. My remit covers engineering design, manufacturing engineering, automation, information technology and operational-technology security.

I began as an apprentice fitter and machinist in 1989. Before Kestwater I worked as a CNC programmer, production engineer, manufacturing engineer and engineering manager in pump, hydraulic and automotive plants. That path shapes the question I ask of any technology proposal: when an instruction reaches a machine or a welder, can we show which approved revision it came from, who could change it and what record proves the result? A model, a network diagram and a robot program are each an answer to that question, or a failure to answer it.

This site describes three decisions in which the better answer cost something. Older machines stayed in service behind a separated network. Defence drawings moved into a controlled system before commercial ones did. A single robotic welding cell replaced the three our owners first preferred. In each case production, commercial or finance colleagues disagreed with me for sound reasons, and I have tried to record their objections beside the outcome rather than after it.

Nineteen machines kept, isolated and watched

Replacing every CNC machine on an unsupported program-loading computer was quoted at A$13.4 million. Network isolation, a controlled program server and four control retrofits cost A$1.9 million and cut controller-related stoppages from 31 hours a month to nine.

Revision errors fell where the thread was built

Revision-related nonconformances on defence work fell from 41 in the 2022 financial year to six in 2025 once models, travellers and inspection records were linked. Commercial work waited eighteen months longer for the same discipline.

One robot, with eight welders as its programmers

A single A$2.9 million cell, qualified for two repeatable joint types, reached 58 per cent arc-on time against 22 per cent for manual welding of those joints. No welder lost a position; eight experienced tradespeople now program and run it.

Current focus

I am replacing the oldest programmable logic controllers on our cranes and plasma-cutting tables in an order set by spare-part risk, and extending the controlled drawing path to the Henderson workshop without weakening its separation from commercial systems.

Conversations I welcome

I am seeking a first non-executive role, ideally on an audit and risk or technology committee of a manufacturer, defence-industry supplier or infrastructure business, with about twenty-two days a year available subject to my employer's consent.

The leadership record

Trusted with consequential decisions.

Formation

  • Graduate certificate in industrial control-system securityVelmarch Institute · 2018
  • Bachelor of Engineering (Mechanical)Cradenfield University · 2000
  • Trade certificate in fitting and machiningArdrossmoor Technical College · 1993
Alistair brings the board the register before the recommendation. When he asked us to keep nineteen old machines, he also showed us exactly how we would know if that judgement had been wrong.
Fiona StrachwellIndependent chair, Kestwater Engineering
The full record ↗